Ballard Locks large chamber to close for repairs

The Hiram M. Chittenden Locks large chamber will close to all vessel traffic 6:30 a.m. October 12, for the first of four scheduled extended closures to begin replacing the chamber’s filling culvert valves.

It will remain closed for up to 53 days, with a scheduled reopening December 3. That’s a month longer than the typical November annual maintenance closure two to three week time frame. The small chamber will remain open during this time and vessels up to 28-feet wide by 123-feet long are able to use it.

https://www.nws.usace.army.mil/Media/News-Releases/Article/1987329/chittenden-locks-large-chamber-closing-up-to-53-days-october-12/

 

Construction Update- October 8

Customer Service Facilities
(Restroom Project)
Construction Update- October 8, 2019

This Week:
o M-3 South Restroom
• Site excavation is finished
• Slab-forming and under-slab utilities installation is underway

o M-4 Central Restroom
• Pre-excavation activities are in progress, including soil-sampling, erosion control, asphalt saw-cutting and temporary jobsite power.

o M-6 North Restroom
• Parking spaces within the building site have been posted with “No Parking After 10/12”

Looking Ahead:
o At M-4 Central, excavation will begin on October 10th
o Construction fencing will be set up around the M-6 North Restroom building site on early on October 14th

Please contact the marina office at 206-787-7236 for further information or send an email to
Shilshole-Outreach@portseattle.org

Construction Update- October 1

This Week:
o M-3 South Restroom
• Excavation nearing completion
• Slab forming and in-slab utilities installation to begin

M3 excavation, photo courtesy of Gary Peterson

o M-4 Central Restroom
• Construction fencing erected on October 3rd
• Pre-excavation activities (soil sampling, erosion and sedimentary controls)

o M-6 North Restroom
• Parking spaces within the building site posted with “No Parking After 10/12”

Looking Ahead:
o At M-4 Central, excavation will begin on October 12th
o Construction fencing will be set up around the M-6 North Restroom building site on October 14th

Please contact the marina office at 206-787-7236 for further information.

Construction Update

SHILSHOLE BAY MARINA
Customer Service Facilities
(Restroom Project)
Construction Update- September 24, 2019

This Week:

o M-3 South Restroom building site:
• Test holes have been dug for environmental testing on dirt for proper disposal
• Tentative time frame to start excavating site depends on results for environmental testing

o M-4 Central Restroom:
• Construction fencing will be set up October 3rd
• Erosion control measures will set up after fencing is in place
• Excavation is expected to start October 8th

Looking Ahead:

• Signs will be posted for M-6 North Restroom announcing “No Parking after 10pm October 12th”
• Construction fencing will be set up around the M-6 North building site

Please contact the marina office at 206-787-7236 for further information or send an email to Shilshole-Outreach@portseattle.org

Construction Update

SHILSHOLE BAY MARINA
Customer Service Facilities (Restroom Project)
Construction Update- September 17, 2019

This Week:

1. At the M-3 South Restroom building site, construction fencing was set up at two locations. One is for the construction site itself and the other is for a material and equipment laydown area (by Seaview Avenue).
2. This Wednesday through Friday, preconstruction activities such as erosion and sediment control measures, and temporary power connections will take place.
3. On Friday, around mid-day, a planned power outage will impact the M-2 restroom building. Lighting, HVAC and hand dryers will be inoperable for approximately 30 minutes while modifications are made.
4. Marina wide, all parking lot and promenade pole lights have been adjusted to operate at maximum intensity during overnight hours. The motion sensing feature has been deactivated. This change will stay in effect for the duration of the project.

Looking Ahead:

Excavation of the M-3 South Restroom site will begin on Monday September 23rd and will continue for at least six days.
1. On Friday September 20th, signs will be posted at the M-4 Central Restroom construction site announcing “No Parking After 10:00 PM on October 1st “.
2. On Thursday October 3rd, construction fencing will be set up around the M-4 Central building site.

Please contact the marina office at 206-787-7236 for further information.