Construction Update-Nov. 1

Bi-Weekly Update:

M3 foundation; photo courtesy of Gary Peterson, E-dock

New M3 Building
• Under slab utility installation complete and working on rebar installation.
New M4 Building
• Under slab utility installation continues.
New M6 Building
• Completed excavation, sub grade passed, and starting backfill.

Looking Ahead:
New M3 Building
• Continue with rebar installation and prep for slab placement
• Start building installation.
New M4 Building
• Continue with installation of utilities.
• Start installation of forms for slab on grade.
• Start installation of rebar.
New M6 Building
• Place base course and test for compaction.
• Start installation of under slab utilities.

Please contact the marina office at 206-787-7236 for further information or send an email to
Shilshole-Outreach@portseattle.org

restroom project and plans

tree removal

About a month ago I filed a complaint with the Seattle Buildings and inspection department objecting to the removal of four trees just to the North of the marina office. I objected that these were mature trees that were possibly within the shoreline management acts distance from the water that would require a permit. The cities tree removal ordinance (SMC 25.11) requires a permit also.
The complaint was assigned to a Betty Rasmussen. I spoke with Betty today and she says that she contacted a Robert Hoyman at the port asking for a arborist report. The file number of the complaint is 009478-19CP. I offered to Betty to be the point person for this issue since she is swamped with complaints. Post to this forum and I will relay to Betty.
This is not the first time the marina has removed trees with no apparent notice. I mostly want to know where substitute trees have been planted as required under the law. I will update the community as further developments occur. Thank you. Dan Kruzich, D-11.

Ballard Locks large chamber to close for repairs

The Hiram M. Chittenden Locks large chamber will close to all vessel traffic 6:30 a.m. October 12, for the first of four scheduled extended closures to begin replacing the chamber’s filling culvert valves.

It will remain closed for up to 53 days, with a scheduled reopening December 3. That’s a month longer than the typical November annual maintenance closure two to three week time frame. The small chamber will remain open during this time and vessels up to 28-feet wide by 123-feet long are able to use it.

https://www.nws.usace.army.mil/Media/News-Releases/Article/1987329/chittenden-locks-large-chamber-closing-up-to-53-days-october-12/

 

Construction Update- October 8

Customer Service Facilities
(Restroom Project)
Construction Update- October 8, 2019

This Week:
o M-3 South Restroom
• Site excavation is finished
• Slab-forming and under-slab utilities installation is underway

o M-4 Central Restroom
• Pre-excavation activities are in progress, including soil-sampling, erosion control, asphalt saw-cutting and temporary jobsite power.

o M-6 North Restroom
• Parking spaces within the building site have been posted with “No Parking After 10/12”

Looking Ahead:
o At M-4 Central, excavation will begin on October 10th
o Construction fencing will be set up around the M-6 North Restroom building site on early on October 14th

Please contact the marina office at 206-787-7236 for further information or send an email to
Shilshole-Outreach@portseattle.org

Construction Update- October 1

This Week:
o M-3 South Restroom
• Excavation nearing completion
• Slab forming and in-slab utilities installation to begin

M3 excavation, photo courtesy of Gary Peterson

o M-4 Central Restroom
• Construction fencing erected on October 3rd
• Pre-excavation activities (soil sampling, erosion and sedimentary controls)

o M-6 North Restroom
• Parking spaces within the building site posted with “No Parking After 10/12”

Looking Ahead:
o At M-4 Central, excavation will begin on October 12th
o Construction fencing will be set up around the M-6 North Restroom building site on October 14th

Please contact the marina office at 206-787-7236 for further information.

Construction Update

SHILSHOLE BAY MARINA
Customer Service Facilities
(Restroom Project)
Construction Update- September 24, 2019

This Week:

o M-3 South Restroom building site:
• Test holes have been dug for environmental testing on dirt for proper disposal
• Tentative time frame to start excavating site depends on results for environmental testing

o M-4 Central Restroom:
• Construction fencing will be set up October 3rd
• Erosion control measures will set up after fencing is in place
• Excavation is expected to start October 8th

Looking Ahead:

• Signs will be posted for M-6 North Restroom announcing “No Parking after 10pm October 12th”
• Construction fencing will be set up around the M-6 North building site

Please contact the marina office at 206-787-7236 for further information or send an email to Shilshole-Outreach@portseattle.org